Center Line Technologies recently completed a $1.25 million dollar project for General Motors in Pontiac which entailed the following:

  • Complete multi-pair copper voice backbone cabling system with 8,400 pairs of terminations at the MDF to 110 style blocks.
  • Eleven telecommunication closets with an average of approximately 800 pairs of terminations to 110 style termination blocks, and cross connections and terminations (via 25 pair cables) to patch panels.
  • Four 1,800 pair copper backbone cable splices.
  • Horizontal cabling installation totaling approximately 2.25 million feet of CAT 5e Commscope cable.
  • All terminations and testing for the above (approximately 9,300 drops for 3,100 locations).
  • A 20 year Siemon Cabling Systems UltraLink Warranty was obtained for the entire installation.
  • All RF coaxial cabling, terminations, and testing for the video transmission system.
  • Complete bonding backbone system.
  • Air blown fiber optic cabling system for the entire complex totaling approximately 5.5 miles of cabling and 720 terminations.